October 2010 report
article by: Alan Bielby

Some of the Broadway team with the beginnings of the platform walls. (Photo: Alan Bielby)

DEVELOPMENTS AT BROADWAY
A team of volunteers have been working steadily at the site
since early 2009. Initially, work focussed on site clearance and
investigation - to expose what was left of the old station and to
decide what, if anything, could be re-used. Our investigations have
shown that the old station was demolished without thought for the
future so very little was left intact; most parts above ground were
thoroughly demolished and then either piled in banks on each side
of the track or removed completely, while the remaining foundations
are showing the effects of time so cannot be re-used.
On the positive side, our Board took a decision to aim to
rebuild the station in the same style as the original, albeit with
increased platform lengths to cater for the longer anticipated
stopping trains and with a station building which externally
replicated as far as possible the original design, whilst
internally satisfying building regulations and the needs of our
present day visitors. We are lucky in that the Broadway Station
building was almost identical to the one left standing at
Toddington apart from being a mirror image. This means that we can
learn a lot from examining the features of Toddington that make it
most definitely a Great Western Railway design.
Since then we have been building up a picture of what is needed
at Broadway, both in terms of what should be incorporated inside
the building - booking office, booking hall, waiting room, shop,
snack bar etc; and what must be provided within the site - toilet
block, a large car park, disabled parking, access for tour groups,
etc. The site is constrained by being partly on an embankment and
partly in a cutting so we have been obliged to expand our field of
investigation to ensure that these features can be provided.
With a growing picture of what we need to start reconstruction,
our Railway colleagues have been hearing of our need for basic
building materials and so have pointed us in various directions
where imperial sized bricks can be recovered. In addition to our
ongoing brick recovery on site, which has so far gained us around
4000 imperial sized blue bricks, we have recovered a similar number
of old red bricks from a church schoolyard in Coleford and several
hundred chamfer blue bricks from an old railway building being
demolished at Taunton (look at the wall of any GWR station building
and you will see them about two feet above ground level). We are
always on the lookout for imperial bricks - we need around 20000 of
each! So if you are aware of any going for free (and not too far
away or too close to operational lines), please let us know.
We have recently had the loan of an excavator - with skilled
driver - from Neatford Construction, a local road maintenance
company, and have achieved a lot in further brick searches, site
clearance, and, significantly, the trenching to pour a second batch
of concrete. This has now given us over 200ft (60m) of poured
foundation - sufficient to initiate platform construction.
Construction started in mid-August and initially we aim to
construct at least the first 100ft of platform face. Our thanks
must also go to Neil Booth of Railwayana Auctions fame for donating
concrete blocks and arranging the most welcome support from leading
local building suppliers.
We have compiled sufficient information to confirm that the
original track alignment through the station complied with the old
GWR plans and so can be confident that we can restore this
alignment (using the nearby Evesham Road Bridge as a datum point)
and set out the platform face appropriately. With new strong
foundations we can erect the platform face to provide a traditional
blue brick facing backed by modern concrete block-work. A strong
platform design is necessary in view of the local clay soils and a
mix of cutting and embankment surroundings.
With our first step into construction under way the on-going
construction will depend on funding - currently the Railway's focus
is understandably the repair of the major slip that has occurred
south of Gotherington. See other parts of this website for the
latest progress on this.
In parallel with this activity, we are working on the site
layout and building design so that when further funds become
available we will be able to put them to good use.
We have also initiated our own fund raising efforts and have a
steadily growing Friends of Broadway Station group as well as
placing a Broadway Station stand at major events both on the
Railway and in the area. If you would like further information on
these activities or have any other queries, please email me through
enquiries@gwsr.com or
telephone me on 01386 584891.
You can also see our week to week activities on the unofficial
blog website run by Bill Britton, one of our stalwart volunteers,
at http://broadwaygwsr.blogspot.com/. In
addition you can visit our station site (future post code WR12 7DF)
to see our progress and, if it is a Saturday or Wedneday, chat to
the guys working there.
Alan Bielby, Broadway Group
October 2010