June 2007 Progress report
article by: John McMillan

P&O was on display on the Toddington unloading road during the 2007 Cotswold Festival of Steam. Thanks to Darin Fryatt for the picture.

Hard work by our contractor has seen the final fitting up of the
last of the big sheets of the boiler cladding. In addition,
the cover over the dome was positioned and work was completed on
the boiler bands and their tensioners, and the whole assembly was
put in place. The loco looked very smart indeed and is clearly
recognisable as a rebuilt Bulleid Merchant Navy. The undersides of
all the cladding have been painted up to and including a final
gloss coat, which will keep any corrosion from the inside to a
minimum. The outside surfaces are still in grey primer, as
the final finish of the loco will be judged by the quality of the
paintwork on the boiler cladding.
With the boiler raised for completion of the cladding, we took
the opportunity to have a final fettling and tidying of all the
large copper pipe work between the frames. These pipes supply
steam to accessories such as the steam brake, sanders and drain
cocks, etc. There's just one small lubrication pipe run remaining
to be completed between the frames. Machining of the new belly
plate is complete and it is ready to be fitted up to the underside
of the boiler.
However, in early January we had to urgently prepare the loco
for moving out of the David Page shed, because of the major civil
engineering works being undertaken in Toddington Yard, and changes
in the use of the four roads within the shed. The first
priority was to get the boiler back down on to the chassis;
lowering the boiler was hard work but relatively
straightforward. The main difficulty was to try keeping the
boiler aligned with the chassis during the descent, and much
jacking and adjustment was needed before the boiler landed on the
correct spot. Once the boiler was down, the cab could be slid
back into position.
Before the loco could be moved we had to oil up all the moving
parts. The loco hadn't moved for three years since the cab
was re-fitted, so all the bearing surfaces were very dry.
Lubrication was a lengthy process, but once the wheels had made one
full revolution the chassis glided along smoothly, indicating that
all was still well with the axle bearings.
Anticipating a possible eventual loss of our covered
accommodation, some time ago we purchased a set of custom-made
tarpaulin covers for the loco, and these have been brought out of
store for use in keeping the worst of the Cotswold rain out of the
vulnerable parts.
Since the loco was moved, the late winter weather has severely
curtailed any work on the chassis, but inside the workshop we have
a volunteer 'trainee' who has taken on the painstaking task of
preparing the mating surfaces on the steam manifold in the
cab. This is a job we've put off for some time, so we are
grateful for the work being done. There are nine surfaces on the
manifold, each of which requires to be made perfectly flat to
effect a steam-tight joint with the fitting that goes there.
Using gaskets here would be very risky, since if one blew the cab
would be instantly filled with scalding steam at full boiler
pressure, with potentially disastrous consequences for anyone on
the footplate. By the time he's laboriously completed all nine
surfaces on the manifold and their corresponding fittings, our
'trainee' will definitely be an 'expert'!
Work on the tender brake system has continued throughout the
winter, and we were very pleased to make contact with a specialist
fabricator who can make up the vacuum reservoir cylinders for
us. We had the 'dished' ends made some time ago, and these
have since been provided with their pipe fittings. This next part
of the job will be undertaken off-site where the cylindrical part
of the reservoir will be rolled to shape, seam welded, then have
the ends welded in place. When in service, condensation
builds up inside the cylinders, so each will have a drain hole and
fitting welded into the bottom. Finally, the whole assembly
will be treated with a process similar to galvanizing to prevent
internal corrosion. We are hoping to have all three completed
cylinders back in the next few weeks.
Whilst the hurried move at short notice from the David Page shed
was a disappointing development, we have had to look at the
opportunities that the move presents, and plan our work
accordingly.
P&O on display at the Festival of Steam
We have known for a long time that restoration work on the
boiler cannot be completed at Toddington, and the loco would have
to be moved outside for the boiler to be lifted off the loco for
taking off site for fitting of tubes, etc., and undertaking a steam
test. So we have obtained quotations from several companies
for carrying out the work to complete the boiler restoration, and
we are now negotiating with a boiler engineering company to fit a
full set of tubes and complete all the work required to carry out a
steam test. If all goes to plan, the boiler will be taken
from Toddington in mid-summer for this work to be carried out, and
meanwhile we will then be able to fit the centre ash pan
(impossible with the boiler in place), and also hopefully fit the
inside connecting rod.
Eventually, later this year a fire should be lit in the boiler
for the first time in over forty years. This will not complete the
restoration project by any means, and the large hole in our
finances created by this work will need filling
again. However, it will certainly be the most
significant development in this long-running restoration for many
years, and a positive step in the right direction, clearly
demonstrating our serious intention to have this splendid
locomotive running again.