April 2009 S&T Report
article by: Andy Protherough
First of all a brief introduction. My name is Andy Protherough
and I have been a working volunteer with the S&T Department for
a little over two years. Fortunately, working nights (midnight to
0900a.m.) for a local dairy, gives me the opportunity to work
alongside a small team of dedicated guys during the working week
rather than during the family weekend.
Projects covered during the week include the refurbishment /
restoration of all aspects of signaling equipment from small nuts
and bolts to a complete bracket signal such as seen south of
Gotherington station, at our workshop* within Winchcombe yard. Once
these refurbs are complete, the items either go into storage or out
to various locations along our line. Larger projects undertaken
include the fitting out of Gotherington signalbox, 'planting' and
fitting of signal posts, installation of point motors, point
rodding, electrical cabinets, etc. all under the watchful eye (pipe
and cup of tea) of Malcolm Walker! Our weekday gang usually
consists of myself, John (dad) Protherough, Carl Smart, Ron
Redding, John Nicholls, Richard Collier and Tony Long and
Stuart.
We also have a dedicated Wednesday gang of electrical fitters,
namely Ed Reilly, Kevern Oliver, John Lewis and Harry Rowe. Our
'Mr. Electrics' at Winchcombe comes in the shape of Neil Carr.
I hope to bring regular updates of our progress at the beginning
of each month, reporting on news of what has been achieved during
the previous month. To bring you up to date for 2009, I have
included below news for January, February, March and April. All
being well, the next update will be during the first week of June
for May. Hope you enjoy the read…..
P.S. 95% of our 'workshop' at Winchcombe is the great outdoors.
Drilling, cutting, painting……you name it and it's done outside. So
if anyone out there has a £100000 gathering dust under the
mattress, we do have plans drawn up for a permanent workshop to be
erected behind santas grotto. Cheque made payable to…
JANUARY 2009
To start the week off, Monday 5th brings a layer of snow to the
Cotswolds. Malcolm and myself spend a number of hours clearing snow
from points and FPL's (Facing Point Locks) around Winchcombe to
allow movement of the railcar. Tuesday saw the railcar refuse to
start, requiring a jump start from John P's Landrover Discovery.
During this week, John P. and myself dismantle Toddington
motorpoint 20 along with the associated blades, stretcher bars,
fixing bolts and coupling bars. Electricity supply disconnected by
Neil Carr to Lever Locks 1,2 and 3 in the 'box.
A start was made on the lamp hut next to Toddington signalbox to
clear many years of accumulated rubbish to make room for a wet day
workshop. This was to take a number of trips back to the skip at
Winchcombe via the railcar over a two week period.
Wednesday and Thursday saw the continuation of rubbish clearing
from the lamp hut and the building of a workbench and
shelving.
The second week saw the loading of the scaffold tower onto the
railcar for transfer to Toddington North. This was then erected
around the route indicator signal T22, T23 which was then
dismantled by myself, John P and Carl Smart, loaded onto the
railcar, moved north to the site of new 'E' switch and
offloaded.
Malcolm and Neil meanwhile suffer the cramped conditions under
Toddington 'box drilling and fitting brackets and plates to the
lock fixing bars in readiness for new equipment.
The third week saw the manufacture and fitting of more lock fixing
bars and electric locks and fitting of additional steelwork to
Toddington 'box.
Back at Winchcombe, restored fittings were taken from storage and
put ready for transfer to Toddington along with items such as
concrete blocks for mounting wheels to route signal wires under the
running lines and a large quantity of concrete troughing with lids
to take cables safely from the signalbox to various cabinets in the
north headshunt.
During the final week of the month, the above items were loaded
onto the railcar and transferred to Toddington. Fittings were
offloaded at the signalbox, the troughing and concrete blocks
distributed along the embankment ready for installation.
FEBRUARY 2009
Week commencing 2nd February saw a number of projects. Namely
re-bonding the track circuits through Toddington crossing after
this had been renewed by the p/way dept. The wall of platform 1 was
measured and marked for drilling and fixing wheel casts to carry
signal wires through the platform. The concrete wheel blocks
adjacent to point 12a had over the years subsided quite badly
causing the signal operator to exert a greater amount of leverage
to operate the signals. Therefore these were dug out, straightened
up, leveled and repacked with fresh ballast.
Further work to the locking trays was completed by Malcolm and
Neil under the 'box.
The second week saw over 200 meters of concrete troughing laid
from the signalbox to the south end of platform 2, and then
from the north end to the site of the old route indicator signal
just north of Stow Road bridge. Wednesday saw the uprooting of the
above signal post by JCB Steve and re-planting at it's new
temporary home next to P21, approx. 100 meters further north. This
will eventually be replaced by a bracket signal currently coming
towards the end of it's refurb at Winchcombe.
The third week brings what has in the past been a very exhausting
job. Cable laying. On Monday with the aid of a pair of jacks
strapped to the rails, the cable drum was lifted a few inches above
sleeper tops, the end of the cable attached to the railcar and as
Neil slowly moved the railcar in the Winchcombe direction, so 500
meters of cable was uncoiled. This exercise repeated for the 20
pair and 50 pair cables.
Once uncoiled, each cable was then dragged again by the railcar,
through platform 2 negotiating any obstacles, towards the north
headshunt leaving enough spare cable at the southern end to reach
the inside of the signalbox. Once in place, both cables were then
placed inside the concrete troughing laid out last week.
Tuesday, myself, John P and Carl Smart were tasked to rebuild
the route indicator signal. Being an unseasonably warm day, hauling
heavy cast fittings 30 or so feet skywards brought one or two beads
of sweat from the brow. Apart from the paintwork looking very
tired, at least all the moving parts have been cleaned of years of
neglect and given a generous coating of lubrication.
Thursday brought more cable laying with the 110volt supply to
the new 'E' switch motorpoint.
The last week of the month starts off with the digging of holes at
the base of the route indicator signal to take a number of concrete
blocks for signal wire wheels. Shuttering was formed and fixed in
place at the south ends of both platforms ready for new concrete.
The original concrete having been removed when p/way replaced the
timber sleepers through the crossing at the weekend.
Tuesday has us mixing concrete, ably assisted by Neil Carr on
the mixer, John P on the wheelbarrows, myself and Carl Smart
shoveling and leveling the finished product. Both sides completed
by 2p.m. we all deserved our late lunch, cup of tea (and another
chuff on the pipe - Malcolm). The afternoon saw the completion of
track circuit bonding from the 'E' switch back to Stow Road
bridge.
MARCH 2009
The first week of the month had us planting and concreting
signal wire stakes from Stow Road Bridge to the route indicator
signal. Back at Winchcombe the week was taken up with the extaction
from the yard of a number of electrical cabinets and the subsequent
stripping down and refurbishment, completed by a fresh coat of
paint.
The following week brought together weeks worth of refurbishment
work with the re-building of a bracket signal that will eventually
grace the Toddington North skyline. After much tweaking, the
assembled parts were then numbered and colour-coded for dismantling
in readiness for transfer by railcar to Toddington.
The new ground frame for Toddington is nearing completion by
Malcolm. New flooring has still to be sourced.
Fill in jobs during the past two months has entailed the clearing
up of Winchcombe yard. This has entailed putting items into
stillages, onto pallets or into skips for scrap. Longer term
restoration items have been stored on several goods wagons in the
yard. Once completed, the 'empty' yard will then be at the mercy of
p/way who will be extending the storage sidings with a view one day
to having a covered carriage shed. This will have the advantage of
reducing the amount of weather related maintenance required to our
ageing fleet of passenger stock. Anyone with a few hundred thousand
pounds to spare, please get in touch.
The third week saw the final clearing up of the yard which just
left the job of leveling the site to the JCB.
Non-slip flooring donated by a bracket signal found in the
undergrowth during the above clear up has been modified to fit the
new ground frame. Being of a metal construction, this will reduce
future maintenance requirements. A metal handrail is now being
manufactured by Malcolm using further materials found around the
yard. All parts are being labeled to ease reconstruction when moved
to Toddington.
The final week of March and we are back at Toddington North with
the rail drilling machine for more track circuit bonding.
Unfortunately, we have encountered some very hard rail which our
drills are reluctant to penetrate. On further inspection we have
found these rails to be of manganese, especially around the new 'E'
switch. Various approaches to our drilling has seen the destruction
of two/three drill bits per hole. At £10 per bit this is not good
housekeeping!
Holes are dug and shuttering for the concrete pads for signals T4
and T20 is put in place. The posts for these signals have been
prepared and painted in Winchcombe yard by John Nicholls, John P
and Carl Smart and currently await a visit from our welder to fit a
base plate to each. These will then be bolted to the concrete pads
before fitting out with refurbished parts from storage.
APRIL 2009
Tuesday 7th and finally the concrete goes in to the ground for
T4 and T20. Upon each of the railcar trailers sits a concrete
mixer, two tons of ballast and ten bags of cement, a water
container and a bucket. I man one, John P mans the other. On the
ground is Carl Smart doing sterling work with the wheelbarrow
taking the concrete mix to the hole, tamping and leveling. Malcolm,
along with his trusted friends (pipe and cuppa) make frequent
journeys with the railcar to and from a watering point in the
platform to keep our water containers replenished. One and a half
hours later one hole is filled. A quick brew and the trailers are
moved to the up line to repeat the process on the Malvern
side.
After a very late lunch, some drilling using a hand power drill of
the errant 'E' switch. Again not 100% successful.
Motorpoint moved into position ready for installation.
Second week and we get to bolt down the new motorpoint, fit the
rodding that drives the switch blades and connect the detector
bars. And yes, more drilling and rail bonding.
During the third week, work at Winchcombe sees the refurbishment
and painting of one long and two short ladders that will eventually
provide access to the Toddington North bracket signal.
At Toddington, any new exposed cables are covered and stakes
concreted in. adjustments are made to signals T6 on platform 2, and
T22 + T23 route indicator signal. Neil Carr wires up new motorpoint
back to signal box. Checks made and all is working O.K.
The final week of April has us remove the point rodding/fittings
and concrete stools that made up the south ground frame and
transfer all to its new home at the North head shunt. These will be
reinstalled here possibly during May.
Position of the new home and distant signals at the approach to
Toddington from the north were measured. These will now be
incorporated within the remodeling diagram and the necessary
equipment found, restored and painted at Winchcombe.
While all this has been going on at Winchcombe and Toddington, we
must not forget our team of electrical fitters working away at
Gotherington signal box. As yet we have no fixed date for
completion, but the miles of wiring and banks of relays and
switches continues to grow! Hope you guys don't think we have
forgotten you, as we often remark on how nice it must be working
inside 'the box' when the heavens open full throttle here at
Toddington North! Keep up the good work, and Ed, remember to use
only managed forests for your paperwork….