June 2009 S&T Report
article by: Andy Protherough
Week ending 6th June
With the aid of the P/Way train, S&T Dept. assist with line
side clearance of P/Way materials (old sleepers, chairs, etc)
S&T materials (concrete troughing, old bonding wires, etc) and
any other materials/rubbish, between Winchcombe and Cheltenham
Racecourse. This followed an incident the previous week when
certain items were deliberately laid across the track by persons
having total disregard for the safety of others. As seen from the
photo on the right, a large amount had been cleared up by the time
we had reached Gotherington and we still had to reach
Cheltenham.
Back at 'HQ' the continuing restoration of various items goes
on. Various lengths of angle iron previously measured and cut get
the good news with a wire brush attachment on the disc cutter.
Cams, wire adjusters and lever frame stabilizing bars get the same
treatment and the all receive a coat of red oxide paint. These will
then further the extension of Toddington lever frame within the
signalbox. Two crows nests for signals T4 and T20, and eight down
rods are all taken from storage, cleaned of paint, cut and prepared
for welding before given a coat of red oxide paint.
Week ending 13th June
Removal of tree and weed growth from behind Toddington signal
box. Once cleared, a layer of weed suppressing material was
unrolled and stone chippings put down to create an access path.
Malcolm Walker and Neil Carr continue to extend the lever frame
above and below floor level inside the 'box to accommodate two
extra levers. These will operate signal T32 'Outer Home Approaching
From Broadway', and a release lever to enable working northbound
from Toddington. This has involved the cutting to size of 'C'
profile girders, manufacture of brackets, and the restoration of
cams, saddles and bolts. The temporary fitting of some locking
trays required to give fixing point measurements for support
brackets.
Week ending 20th June
Another 190 yards of track is drilled and bonded from Toddington
North Headshunt point, northwards. After spending the first 90
minutes drilling just six pairs of holes (two panels of very hard
rails), we eventually came across some 'softer' rails which speeded
up our rate of progress no-end.
Malcolm & Neil drill and fit new stretcher bars to NHS
point.
The rest of the week is taken up with the trimming to size and
cleaning of locking trays prior to giving a coat of red oxide
paint. Eight lever catch rods, catch handles, pins and bolts
cleaned and painted.
Thursday sees Malcolm Walker standing in for an absent signalman
to give a lecture on the principles of a working signal box to 90
local pupils.
Week ending 27th June
Carrying on from where we left off last week, more drilling and
bonding until we reach manganese rail just short of Stanway
viaduct. This rail already has holes drilled and fitted with a bung
which requires a special attachment. These will be purchased and
fitted at a later date.
Two locking trays are drilled and bolted down onto the support
brackets. A large hole has now been cut into the floor of the
signalbox ready to accept the lever frame extension.
Thanks must go to Carl Smart in arranging the laser cutting of
ten new speed restriction signs from local Tewkesbury firm, Emsea.
Once painted yellow and black, these will replace the 'temporary'
wooden signs around Gotherington and Toddington that have been in
place for many years.