TODDINGTON YARD DEVELOPMENT
Following is the schedule for works in the yard at Toddington. Yellow areas indicate work completed.
|
Scheduled Date
|
Work on first phase:
Phase ‘0’
|
Comments
|
|
6-10 Jan
|
Shunt stock in yard to clear site for removal of track. Includes loading of equipment such as locomotive frames, boilers etc on to wagons. Rails prepared for removal
|
Complete on time
|
|
13-17 Jan
|
Lift track, continue to clear site; site meeting with contractor and disconnection of south yard electricity supply.
|
Complete on time
|
|
20-21 Jan
|
Disconnect main line, remove rails and sleepers from sidings 1-3. Complete shunt including placing 2807 and 8F chassis in the David Page shed. Warning signs and fencing
|
Complete on time
|
|
22 Jan onwards
|
Contractors on site excavating trenches for installation of pipe work, electricity and telecommunications ducts and pour concrete raft
|
Delayed because of weather, but complete
|
|
3 Feb onwards
|
Backfilling of trenches
|
Completed
|
|
10-18 Feb
|
Start reinstallation of main line and sidings.
|
Main line and siding 1 completed.
|
|
10-18 Feb
|
Disconnect unloading road (siding 5) and sections of sidings 6, 7 and 8 in front of David Page shed. Reconnect electricity supply
|
Disconnection of unloading road to be delayed for loco arrivals and departures until 9th March.
Roads 6 and 7 disconnected 4th March.
|
|
24 Feb -2 March
|
Complete excavation and prepare ground for reinstatement of track. Complete and ballast main line. Complete installation of drainage plant. Reopen main line, unloading road and sidings 1 and 2 for traffic.
|
Drainage plant installation in progress. Work on siding 2 to be completed weekend of 10th/11th March. Other work completed.
|
|
26 March
|
Revised date: reinstate severed unloading road, siding 5
|
|
|
12-23 Mar
|
Contractors excavate trench across sidings 5 to 8 for drainage
|
|
Phase ‘1’ works – subject to revision
|
Date
|
Work on ‘Phase ‘1’
|
Comments
|
|
3-4 March
|
Return stock from temporary storage to sidings; return siding 1 to traffic. Replace sleepers and rail on sidings 6 and 7
|
|
|
10-11 Mar
|
Weekend shunt to finalise location of stock in David Page shed; tidy up site
|
Shunt completed on 4th March.
|
|
17-18 Mar
|
Removal of remaining rails and sleepers from site of new pits
|
|
|
24-25 Mar
|
Lay levels etc. in preparation for excavation of new pits by contractors
|
|
|
31 Mar onwards
|
Complete any remaining outstanding work
|
|
|
2 April onwards
|
Start of work on pit excavation
|
|
|