Work Schedule

TODDINGTON YARD DEVELOPMENT

Following is the schedule for works in the yard at Toddington. Yellow areas indicate work completed.

Scheduled Date

Work on first phase:

Phase ‘0’

Comments

6-10 Jan

Shunt stock in yard to clear site for removal of track. Includes loading of equipment such as locomotive frames, boilers etc on to wagons. Rails prepared for removal

Complete on time

13-17 Jan

Lift track, continue to clear site; site meeting with contractor and disconnection of south yard electricity supply.

Complete on time

20-21 Jan

Disconnect main line, remove rails and sleepers from sidings 1-3. Complete shunt including placing 2807 and 8F chassis in the David Page shed. Warning signs and fencing

Complete on time

22 Jan onwards

Contractors on site excavating trenches for installation of pipe work, electricity and telecommunications ducts and pour concrete raft

Delayed because of weather, but complete

3 Feb onwards

Backfilling of trenches

Completed

10-18 Feb

Start reinstallation of main line and sidings.

Main line and siding 1 completed.

10-18 Feb

Disconnect unloading road (siding 5) and sections of sidings 6, 7 and 8 in front of David Page shed. Reconnect electricity supply

Disconnection of unloading road to be delayed for loco arrivals and departures until 9th March.

Roads 6 and 7 disconnected 4th March.

24 Feb -2 March

Complete excavation and prepare ground for reinstatement of track. Complete and ballast main line. Complete installation of drainage plant. Reopen main line, unloading road and sidings 1 and 2 for traffic.

Drainage plant installation in progress. Work on siding 2 to be completed weekend of 10th/11th March. Other work completed.
 

26 March

Revised date: reinstate severed unloading road, siding 5


 

12-23 Mar

Contractors excavate trench across sidings 5 to 8 for drainage

 

Phase ‘1’ works – subject to revision

Date

Work on ‘Phase ‘1’

Comments

3-4 March

Return stock from temporary storage to sidings; return siding 1 to traffic. Replace sleepers and rail on sidings 6 and 7


10-11 Mar

Weekend shunt to finalise location of stock in David Page shed; tidy up site

Shunt completed on 4th March.

17-18 Mar

Removal of remaining rails and sleepers from site of new pits


24-25 Mar

Lay levels etc. in preparation for excavation of new pits by contractors


31 Mar onwards

Complete any remaining outstanding work


2 April onwards

Start of work on pit excavation